green inc. uses the following activity rates from its activity-based costing to assign overhead costs to products: activity rate setting up batches $59.06 per batch processing customer orders $72.66 per customer order assembling products $3.75 per assembly hour data concerning two products appear below: product a product b number of batches 84 50 number of customer orders 32 43 number of assembly hours 483 890 how much overhead cost would be assigned to product a using the activity-based costing system? group of answer choices $9,097.41 $4,961.04 $135.47 $81,146.53