vanessaskye6414 vanessaskye6414 23-05-2023 Business contestada 1. Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000. Show work and provide a detailed explanation of the results.