Manufacturing has gone out on bid for
a regulator component. Expected demand is 700 units per month.
The item can be purchased from either Allen Manufacturing or
Baker Manufacturing. Their price lists are shown in the table.
Ordering cost is $50, and annual holding cost per unit is $5.
ALLEN MFG.
BAKER MFG.
QUANTITY
UNIT PRICE
QUANTITY
UNIT PRICE
1-499
$16.00
1-399
$16.10
500-999
15.50
400-799
15.60
1,000+
15.00
800+
15.10
a) What is the economic order quantity?
b) Which supplier should be used? Why?
c) What is the optimal order quantity and total annual cost of
ordering, purchasing, and holding the component? Px