Equipment constructed for a customer for an agreed price of RM18,000. This has recently been completed at a cost of RM16,800. It has now been discovered that, in order to meet certain regulations, conversion with an extra cost of RM4,200 will be required. The customer has accepted partial responsibility and agreed to meet half the extra cost.