The value of the work completed today is $60 million. The project is budgeted to cost $77 million. The value of the work planned to be done to this point is $78.9 million. What does the schedule performance index (SPI) for this project tell you? Selected Answer: You are progressing at 76 percent of the rate originally planned. explain why is this the answer