A project estimator is developing a cost estimate for construction of a new diagnostic imaging wing. The projected costs are:
Fixed equipment installation charges $700,000
Site isolation $50,000
Annual utilities $425,000
Construction materials $1,200,000
Portable equipment $900,000
Annual depreciation $275,000
What are the expected contractor expenses?
A) $2,200,000
B) $3,475,000
C) $3,750,000
D) $4,200,000