monaec5180 monaec5180 21-03-2024 Business contestada You are the project manager of the LKG Project. The project has a budget of $290,000 and is expected to last three years. The project is now ten-percent complete and is on schedule. What is the BAC?a. $290,000b. $29,000c. $9,666d. $96,666