in the given image, three activities A, B and C are connected in a series to form a path. The sequence followed for representation along the activity arrows is as follows: optimistic time-mostly time pessimistic time. What is the variance of the path?

7-10-18

C

6

OPTIONS

5,72

5.16

4.35

6.5​