In _______, the company always needs to have new projects coming in as other projects are completed, in order to maintain a high applied-time rate for the functional staff.A. an autonomous project organizational structureB. a functional organizational structureC. a matrix organizational structureD. a project management office

Respuesta :

Answer:

The correct answer is a matrix organizational structure.

Explanation:

The matrix structure of an organization divides the authority, both by functional area and by project. In a matrix structure, each employee responds to two immediate supervisors: a functional supervisor and a project supervisor. The functional supervisor is responsible for supervising employees in a functional area such as marketing or engineering. Project supervisors manage a specific and often transitory project. They absorb employees from various functional areas to complete their project teams. This type of organizational structure has several advantages.