Answer:
The answer is: National will succeed in its claim for compensatory damages only (no consequential or punitive damages).
Explanation:
Overland's failure to perform breached the contract it had with National. So National can sue to recover the costs of renting the pump for the five days delay. Any expenses that are caused by a contract breach may be recovered as compensatory damages.