The Development Team should have all the skills and competencies required to...
A. Turn Sprint Backlogs into Increments of potentially releasable product.
B. Deliver Sprint Backlog items to QA/QC department
C. Complete the project in time and within budget
D. Plan the whole project and complete it according to the plan

Respuesta :

Answer:

(A) Turn Sprint Backlogs into Increments of potentially releasable product.

Explanation:

The Development Team is a self-organizing, cross-functional, group of people that should be capable of completing the Sprint Backlog items. And not every kind of delivery is acceptable in Scrum, it should be "potentially releasable Increments of the final product of the project", to help stakeholders give feedback.