Answer:
$750 favorable ; $200 unfavorable
Explanation:
The computations are shown below:
For fixed overhead budget variance:
= Budgeted fixed overhead - actual fixed overhead
= $47,420 - $46,670
= $750 favorable
For fixed overhead volume variance:
= Budgeted fixed overhead - standard fixed overhead cost allocated to production
= $47,420 - $47,220
= $200 unfavorable
Hence we consider all the given information