Respuesta :
Answer:
Schedule performance index (SPI) = 1.25
Explanation:
Earned value (EV)- planned value (PV) = Schedule variance (SV)
25000 - PV = 5000
collecting like terms means taking PV to the right-hand side of the equation & 5000 to the left-hand side of the equation.
25000 - 5000 = PV
PV = 20000
Schedule performance index (SPI) = EV ÷ PV
SPI = 25000 ÷ 20000 = 1.25
Answer:The answer is 1.25
Explanation:
To calculate SPI, we use the formula SPI = EV ÷ PV
EV = $25,000, PV = unknown , SV = $5,000
SV = EV - PV
5,000 = 25,000 - PV
Making PV the subject of formula
PV = 25,000 - 5,000
PV = 20,000
SPI = 25,000 ÷ 20,000
SPI = 1.25
Since it is greater than 1, the project is on track and has a favourable conditions