When working well, the issue management process:

a. Is static and never pulls in additional information that would disturb the balance.

b. Generates two specific options for each issue.

c. Minimizes dialogue with the stakeholders and focuses on short-term survival.

d. Continuously cycles back to the beginning and repeats.

Respuesta :

Answer: The correct answer is

d.) Continuously cycles back to the beginning and repeats.

Explanation: An issue management is a process that helps you deal with issues fast and efficiently. It keeps your project on track. This issues may arise from customers, suppliers or even directly from the project.

An issue management process involves steps to resolve it. To know one which is working well it will continuously cycle back tothe beginning and repeat.