The ____ provide(s) schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.
a.activity list c.activity descriptions
b.milestones d.activity attributes

Respuesta :

Answer:

The correct option is option D, which is activity attributes.

Explanation:

As per the question the the set is a wholesome of schedule related information about each activity including the predecessors, successors, logical relationships and other information adjacent to this. In this context

Option A is not true because it is just the list of all the possible activities

Option B is not true as it does not provide sufficient information regarding the resources, constraints, and imposed dates.

Option C is not true because it does not provide the information regarding the predecessors, successors, logical relationships and lead-lags.

Option D is true only as it encapsulates all of the items mentioned in the question.