Answer:
The correct answer is E.
Explanation:
Giving the following information:
At the beginning of 20x1, the company estimated that manufacturing overhead would be $500,000, and machine hours would total 20,000.
To calculate the estimated manufacturing overhead rate we need to use the following formula:
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Estimated manufacturing overhead rate= 500,000/20,000= $25 per machine hour.