Answer:
B. the direct labor-hours that should have been used to complete the actual output for the period.
Explanation:
Standard hours is the amount of time or hours of labour time taken to complete the period's actual output. It is the time that should have been taken to complete the period's actual output.
It is usually calculated by multiplying standard hours allowed per unit by actual output for the period.