The Plan-Do-Check-Act cycle is best defined as:_______.A. A rigorous procedure for strategic planning. B. A method used to guide problem identification and solution. C. A method first proposed by Joseph Juran. D. All of these statements apply to the definition.

Respuesta :

Answer:

B.A method used to guide problem identification and solution.

Explanation:

Plan-Do-Check-Act cycle(PDCA) ls also known as the Deming wheel or the Deming cycle,is a four-step problem-solving iterative technique used to improve business processes.

  • Plan: Define the problem to be addressed, collect relevant data, and ascertain the problem's root cause or basic cause.
  • Do: Develop and implement a solution; decide upon a measurement to gauge its effectiveness.
  • Check: Confirm the results through before-and-after data comparison.
  • Act: Document the results, inform others about process changes, and make recommendations for the problem to be addressed in the next PDCA cycle.