9. The Tulsa Company allocates overhead based on a predetermined overhead rate of $9.00 per direct labor hour. Job S35 required 8 tons of direct material at a cost of $600.00 per ton and took employees who earn $21.00 per hour a total of 80 hours to complete. What is the total cost of Job S35?

Respuesta :

Answer: Total cost of job S353 is $7,200

Explanation:

Materials required = 8 tons

Cost per ton of material =$600 per ton

DM = Total Direct Materials cost = 8 tons x $600 per ton = $4,800

Direct labor per hour rate = $21 per hour

Total number of hours required to complete the job = 80 hours

DL = Total direct labor cost = $21 per hour x  80 hours = $1,680

Overhead rate = $9 per direct labor hour

direct labor hours = 80 hours

OH = Overhead costs = 80 hours x $9 per direct labor hour =$720

Total Cost = OH + DL + DM = $4,800 + $1,680 + $720 = $7,200