Respuesta :
Answer:
In this question we are supposed to find net present value of the machine
Explanation: Amount in $
0 1 2 3 4
Machine (41,000)
Operation cost (25,000) (25,000) (25,000) (25,000)
Savings from machine 46,000 46,000 46,000 46,000
Net (Outflow)/Inflow (41,000) 21,000 21,000 21,000 21,000
Annuity Factor 1/(1.11)^1 1/(1.11)^2 1/(1.11)^3 1/(1.11)^4
Annuity Factor .901 .812 .731 .659
Net Present Value (41,000) 21,000*.901 21,000*.812 21,000*.731 21,000*.659
Net Present Value (41,000) 18,919 17,044 15,355 13,833
By Adding up all we get=(-41,000+18919+17044+15355+13833)
=24,151
Since project Net present value is positive therefore project can be taken for the business
Answer:
The question is not complete. The full question and the solution is given in the file attached
Explanation: