Respuesta :
Answer:
$29,600
Explanation:
Given that
unit in beginning work in process
= 5,000 × 40 %
= 5000 × 0.4
= 2000
Unit in progress and completed = unit completed - beginning work in progress
= 31000 - 5000
= 26000
Unit in ending work in process
= 2000 × 80%
= 2000 × 0.8
= 1600
Thus
Number of equivalent unit = 2000 + 26000 + 1600
= $29600
Answer:
29,600
Explanation:
Given:
•5000 units work in progress which is 60% completed
•Direct materials added = 34000 units
•units completed = 31000 units
•2000 unit which comprises 80% completed of labour and overhead at end of period.
Therefore,
Units of work in progress completed =
5000 * 60℅
= 5000 * 0.6 = 3000
Thus, remaining units will be:
5000 - 3000 = 2000
Since there were 31000 units completed, we deduct it from work in progress
= 31000 - 5000
= 26000
Units completed as to labour and overhead =
2000 * 80℅
= 2000 * 0.80
= 1600 units
Therefore, the number of equivalent units of production for material costs for the period will be calculated as:
2000 + 26000 + 1600
= 29,600 units