Respuesta :
Answer:
Recommend Project L.Project L has the Highest Net Present Value
Explanation:
We will determine the best project to choose using the Net Present Value Method of Capital Appraisal.
This is the Method possible because the information provided consist of Cash flows, Same Period for Both Projects and the Same Weighted Average Cost of Capital is Provided.
Calculation of Net Present Value of the Projects is as follows :
Project S
Year Financial Calculator Cash flows
0 Cf 0 ($17,000)
1 Cf 1 $5,000
2 Cf 2 $5,000
3 Cf 3 $5,000
4 Cf 4 $5,000
5 Cf 5 $5,000
Cost of Capital = 12%
NPV = 1, 023.88
Project L
Year Financial Calculator Cash flows
0 Cf 0 ($30,000)
1 Cf 1 $8,750
2 Cf 2 $8,750
3 Cf 3 $8,750
4 Cf 4 $8,750
5 Cf 5 $8,750
Cost of Capital = 12%
NPV = 1,541.79
The best project is the one the the highest Net Present Value
Project L has the highest Present Value of $ 1,541.79. Thus, i would recommend Project L