Respuesta :
Answer:
Since NPV is negative (-$73,835.60), the project should be rejected.
Explanation:
Years Amount
0 -$800,000
1–6 $80,000
7 $70,000
8 $60,000
9 $50,000
10 $740,000
In order to determine if this is a good investment or not, we need to calculate the net present value (NPV). If NPV ≥ 0, then the project is good, it NPV is negative, then the project should be rejected.
I will use an excel spreadsheet to calculate the NPV with a 10% discount rate.
We must first determine the present value of the cash flows and then subtract the investment from it.
The present value of the cash flows = $726,164.60 and obviously its smaller than the initial investment: $726,164.60 - $800,000 = -$73,835.60
Since NPV is negative, the project should be rejected.