Answer:
The correct answer is C.
Explanation:
Giving the following information:
In the Proctor Company, indirect labor is budgeted for $24,000 and factory supervision is budgeted for $8,000 at a normal capacity of 80,000 direct labor hours.
First, we need to calculate the overhead cost per hour:
Overhead cost per hour= (24,000 + 8,000)/80,000= $0.4 per hour
Now, we can calculate the total cost of 90,000 hours.
Overhead cost= 90,000*0.4= $36,000