Respuesta :
Answer:
The direct labor efficiency variance is $5,262.50.
Explanation:
Direct labor rate = (standard rate - actual rate)*actual hours worked
= ($22.50*4445) - $94750
= $5,262.50
Therefore, The direct labor efficiency variance is $5,262.50.
Answer:
$3,937.5 favorable
Explanation:
Labour efficiency variance is the difference between the actual time taken to achieve a given production output less the standard hours allowed for same multiplied by the standard labour rate
Labour efficiency variance is determined as follows:
Hours
2,200 units should have taken (2,200 × 2.1 hrs) 4620
but did take 4,445
Efficiency variance ( in hours ) 175 favorable .
× standard labour rate × $22.5
Labour efficiency variance ($) $3,937.5 favorable