Why is the critical path critical?

Select an answer:
• Any delay in the critical path delays the project finish date.
• It represents tasks in which resources are overallocated.
• It represents tasks that are delayed.
• The tasks on the critical path are the most important ones for achieving the project goal.

Respuesta :

Answer:

Any delay in the critical path delays the project finish date.

Explanation:

The critical path method is also said to be the critical path analysis.

It is referred to a set of algorithm which is used to manage the entire activities related to a project.

The longest activity is identified and the time to complete the activity is measured in a critical path method.

It includes the activities and their time duration to be modeled upon.

In case any of the tasks is delayed, the entire project is delayed.