Answer:
$11,700
Explanation:
The computation of the balance in the work in process at the end of the month is shown below:
= Direct material cost + direct labor cost + manufacturing overhead cost percentage of direct labor cost
= $1,800 + $3,300 + $3,300 × 200%
= $1,800 + $3,300 + $6,600
= $11,700
We simply added the direct material cost, direct labor cost and the manufacturing overhead cost so that the ending balance could arrive