Answer:
Predetermined manufacturing overhead rate= $9.8 per machine hour
Explanation:
Giving the following information:
Machine-hours= 50,000
Manufacturing overhead= $490,000
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 490,000/50,000= $9.8 per machine hour