Job 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 2,429 Direct labor-hours 74 labor-hours Direct labor wage rate $ 17 per labor-hour Machine-hours 135 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $18 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be:

Respuesta :

Answer:

Total Job Cost is $6,117

Explanation:

The total cost of the Job 910 is as under:

Direct Material Cost                                                                      $2,429

Direct Labor Cost (74 Labor Hrs * $17 per Labor Hour)             $1,258

Applied overhead (135 Machine Hrs * $18 per Machine Hr)      $2,430

Total Job Cost                                                                                $6,117