Respuesta :
Constraint Equations : [tex]X + 2Y \leq 16 , X + Y \leq 9 , 4X + Y \leq 24[/tex]
Time required for producing sound bar 'X' = 1 hour of machine A , 1 hour of machine B , 4 hour of machine C
Time required for producing flat screen TV 'Y' = 2 hours of machine A, 1 hour of machine B, 1 hour of machine C
So, constraint for machine A (needed for sound bar & flat screen TV) : [tex]1X + 2Y \leq 16[/tex]
Similarly, constraint for machine B (needed for X & Y) : [tex]1X + 1Y \leq 9[/tex]
Also, constraint for machine C = [tex]4X + 1Y \leq 24[/tex]
More for reference : https://brainly.com/question/9405925?referrer=searchResults