Answer:
22 minutes minimum time
Explanation:
In the given scenario Subway sandwich shop has given its processes and time of each process.
We are to calculate the minimum time it will take to process a order. So we add all the times
Below is breakdown of the process time
Jim take orders 5 minutes
Tim prepares bread and Kim prepares filling for the order 7 - 10 minutes. We use 7 minutes since we are looking for minimum time.
Jim then assembles the bread 5 minutes
Time delivers order and takes payment 5 minutes
Total time = 5 + 7 + 5 + 5 = 22 minuites