Answer:
$225,000 income
Explanation:
The company is using percentage of completion technique for the valuation of construction contracts. It expects the revenue of $1,725,000 for a three year contract whose services are to be delivered every year. The company should record its revenue every year whose services are delivered at the end of the year. The company will only record its revenue as unearned revenue at the start of the year.