If it takes 6 men 4 days to dig a hole 3 metres deep, how long will it take 10 men to dig same hole 7 metres deep?

Respuesta :

Step-by-step explanation:

6 men → 4 days → 3 metres

1 man → 24 days → 3 metres

1 man → 8 days → 1 metres

1 man → 56 days → 7 metres

10 men → 5.6 days → 7 metres

therefore, 5.6 days

Topic: direct n inverse proportions

If you like to venture further, do check out my insta (learntionary) where I constantly post math tips! Thanks!

Answer:

It will take 5.6 days for the 10 men to dig the same hole 7 m deep.

Step-by-step explanation:

Laying the data in column

----------------------------------------------------

6 men            3 m hole              4 days

10 men           7 m hole             x days

-----------------------------------------------------

As [tex]6[/tex] men dig a hole in [tex]4[/tex] days, so their rate will be:

[tex]rate\:=\:\frac{4}{3}[/tex]

Then  [tex]6[/tex] men would take [tex]7\times \frac{4}{3}=\frac{28}{3}[/tex] days to dig a hole of depth 7 m.

As we are letting 10 men do work, so they would

take [tex]\frac{6}{10}\times \frac{28}{3}=\frac{28}{5}[/tex] days.

so

[tex]\frac{6}{10}\times \frac{28}{3}=\frac{28}{5}[/tex]

             [tex]=5.6[/tex]   days

Therefore, it will take 5.6 days for the 10 men to dig the same hole 7 m deep.