Assume that the standard cost to make one finished unit includes 2 hour of direct labor at $8 per hour. During April, 22,000 direct labor-hours were worked, 10,500 units of product were manufactured, and total direct labor cost was $160,000. What is the labor rate variance for April

Respuesta :

Answer:

the labor rate variance is $16,000 unfavorable

Explanation:

The computation of the labor rate variance is shown below:

As we know that

Labour Rate Variance = ( Actual Rate - Standard Rate) ×Actual Hours Worked

= ($160,000 ÷ 22,000 direct labor hours - $8) × 22000  direct labor hours

= ($7.27 - $8) × 22000  direct labor hours

= $16,000 Unfavorable

hence, the labor rate variance is $16,000 unfavorable

We simply applied the above formula so that the correct value could come

And, the same is to be considered