Answer:
$115,035
Explanation:
Calculation for what the The net present value of the project is closest to:
First step is to calculate the Present value of annual cash flows
Using this formula
Present value of annual cash flows = Annual Cash Flow * PVA of * (11%, 4 years)
Let plug in the formula
Present value of annual cash flows = $ 137,000 * 3.1024456895909
Present value of annual cash flows =$425,035
Now let calculate the net present value of the project
Net present value of the project =$425,035-$ 310,000
Net present value of the project=$115,035
Therefore the The net present value of the project is closest to: $115,035