Answer:
$4,000
Explanation:
Calculation for what The overhead applied to a job completed during 2021 that used 200 direct labor-hours was
First step is to calculate The predetermined overhead rate
Predetermined overhead rate = $100,000/5,000 direct labor-hours
Predetermined overhead rate = 20 per direct labor-hour
Now let calculate The overhead applied to the job
Overhead applied to the job = $20 per direct labor-hours *200 direct labor-hours
Overhead applied to the job= $4,000
Therefore The overhead applied to a job completed during 2021 that used 200 direct labor-hours was $4,000