Answer:
Total cost= $6,180
Explanation:
First, we need to calculate the predetermined overhead rate:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= (202,100/47,000) + 2
Predetermined manufacturing overhead rate= $6.3 per direct labor hour
Now, we can allocate overhead:
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Allocated MOH= 6.3*100
Allocated MOH= 630
Finally, the total cost:
Total cost= 850 + 4,700 + 630
Total cost= $6,180