Beta Inc. can produce a unit of Zed for the following costs:
Direct material 10
Direct labor 20
Overhead 50
Total costs
per unit $80
An outside supplier offers to provide Beta with all the Zed units it needs at $58 per unit. If Beta buys from the supplier, it will still incur 40% of its overhead. Beta should:____.
A. Buy Zed since the relevant cost to make it is $80.
B. Buy Zed since the relevant cost to make it is $30.
C. Make Zed since the relevant cost to make it is $30.
D. Buy Zed since the relevant cost to make it is $60.
E. Make Zed since the relevant cost to make it is $60.