Compute the Work-in-Process transferred to the finished goods warehouse on April 30 using the following information:

Work-In-Process Inventory, April 30 $175
Direct material purchased during April 150
Work-In-Process Inventory, April 1 200
Direct labor costs incurred 300
Manufacturing overhead costs 250
Direct materials used in production 125

a. $1,170.
b. $1,035.
c. $1,120.
d. $985

Respuesta :

Answer:

$700

Explanation:

The computation of work-in-progress transferred to the finished goods is given below:

We know that  

= Work-In-Process inventory, April 1 + Direct materials used in production + Direct labor costs incurred + Manufacturing overhead costs - Work-In-Process Inventory, April 30

= $200 + $125 + $300 + $250 - $175

= $700

Hence, this is a correct answer