Respuesta :
Answer:
3) The IRR of the project to your company is below 7.9%
Explanation:
As we can see in the question that at 7.9% wacc, the net present value is -$20,420.78
Since the net present value is in negative that shows that the internal rate of return would be less than 7.9%
So according to the given situation, the option 3 is correct
And, the same is to be considered
The IRR of the project to your company is below 7.9% as when the NPV is negative, IRR should be less than the weighted average cost of capital.
What is IRR?
IRR can be defined as the rate of discount at which the present value of cash flows is equal to the present value of the cash outflows.
When the net present value (NPV) is negative, it means that the discounted cash flows are less than the original investment. Furthermore, the discount rate used exceeds the IRR.
When IRR = Cost of capital, NPV is zero; nevertheless, because NPV is negative, IRR must be less than the weighted average cost of capital.
Hence, Option 3. is the correct answer; The IRR of the project to your company is below 7.9%.
To learn more about IRR, refer to the link:
https://brainly.com/question/15177997