Answer and Explanation:
The calculation is given below:
Fabricating department
The budgeted cost is
= $9,280 ÷ 640 hours × 600 hours + $2,300
= $8,700 + $2,300
= $11,000
Grinding department
= $159,600 ÷ 7,600 hours × 9,500 hours + $56,000
= $199,500 + $56,000
= $255,500
In this way the budgeted cost should be determined