Answer:
0.42 orders per minutes
Explanation:
Calculation to determine the process capacity
Process capacity= 4 orders / [6.5+(6 orders*0.5 minutes)]
Process capacity=4 orders / (6.5+3)
Process capacity=4 orders / 9.5 minutes
Process capacity=4 /9.5 minutes
Process capacity= 0.42 orders per minutes
Therefore If Yum and Yee operates with batch sizes of 4 units, ltheir process capacity will be 0.42 orders per minutes