Answer:
Xebec Chemicals
The Takt time in seconds is:
= 90 seconds.
Explanation:
a) Data and Calculations:
Customers' demand per day = 270 units
Number of hours per shift every day = 8 hours
Total time per shift = 480 (60 * 8)
Coffee breaks = 30 minutes (15 * 2)
Meal and rest break = 45 minutes
Total break time per shift = 75 minutes
Net time available for work per shift = 405 (480 - 75)
Takt time = Net time available for work per shift day/Customers' daily demand
= 405/270
= 1.5 minutes
= 90 seconds (1.5 * 60)