A work center had planned outputs of 10, 15, 13, and 20 hours with actual outputs of 12, 14, 13, and 18 hours. The cumulative deviation in output is __________.

Respuesta :

The cumulative deviation in output is -1.

Here, we are to calculate the cumulative deviation in output using the planned outputs and actual outputs

Actual (A)   Forecast (B)      Deviation (A-B)

     12                  10                         2

     14                  15                         -1

     13                  13                         0            

     18                 20                        -2

Cumulative deviation                  -1  

Therefore, the cumulative deviation in output is -1.