The minimum cost of crashing the project that Roger Solano manages at Slippery Rock University by 4 days is $1100
Critical path of the project = Longest path of the project = CE
= 4 + 8
= 12 days
Other Paths = AD
= 6 + 5
= 11 days
In order to reduce project time by 4 days , we need to crash
so as to have total project duration to be 8 days
Cost of crashing = Crashing cost of A, C, D and E
= (1000 - 900) + (600 - 500) + (1200 - 900) + (1600-1000)
= 100 + 100 + 300 + 600
= $1100
Cost to crash per period of Activity A = ($1,000 - $900) / (6 - 5)
= $100
Cost to crash per period of Activity C = (600 - 500) / (4 - 3)
= $100
Cost to crash per period of Activity D = (1200 - 900) / (5 - 3)
= $150
Cost to crash per period of Activity E = (1600 - 1000) / (8 - 5)
= $200
Total = $100 + $50 + $100 + $150 + $200
= $600
The total cost of crashing the project by 4 days is $550
Learn more about cost of crashing:
https://brainly.com/question/4554686