A company that uses job order costing reports the following information. Overhead is applied at the rate of 60% of direct materials. The company has no beginning Work in Process or Finished Goods inventories. Jobs 1 and 3 are not finished by the end of March, and Job 2 is finished but not sold by the end of March

Respuesta :

Based on the percentage completed and the cost of the jobs, total value of work in process inventory at the end of March is $62,480.

What is the Work in Process Inventory?

The work in process will include Jobs 1 and 3 only because job 2 is already done.

Work in process can be found as:

= Cost of job 1 + Cost of job 3

Cost of a single job is:

= Direct labor + Direct materials + Overhead which is 60% of direct materials

Solving for both jobs gives:

= (13,400 + 21,400 + (13,400 x 60%)) + (6,400 + 9,400 + (6,400 x 60%))

= $62,480

Find out more on Work in Process at https://brainly.com/question/7932472.