In order to calculate the Total factory overhead costs: -
We Know,
- Predetermined Factory Overhead Rate = Total Factory Overhead Costs / Direct Labor Hours
- Factory overheads applied to Job 305 = Predetermined overhead rate × Direct labor hours
Statement showing Computations
- Particulars Amount
a)
- Estimated total factory overhead costs 620,000.00
- Direct labor hours 80,000.00
- Predetermined factory overhead rate
- = 620,000 / 80,000 7.75
b)
- Factory overhead applied to Job 200
- = 2500 × 7.75 19,375.00
- Factory overhead applied to Job 305
- = 3000 × 7.75 23,250.00
JOURNAL ENTRY Dr. Cr.
Work in Process Dr. 42,625.00
To Factory Overhead 42,625.00
Therefore, Total factory overhead cost is 42,625.00.