Shirts are made in a process with two resources. The first resource has a capacity of 35 shirts per hour. The capacity of the second resource is 24 shirts per hour. Demand for this process is 20 shirts per hour.

Respuesta :

Total labor content is 4.2143 min per shirt.

What do you mean by labor content?

The sum of all the process stages' individual times is known as the total labor content. For instance, if a procedure has two steps that each take 20 seconds, the total labor time is 40 seconds. Cycle time minus processing time is the definition of idle time.

Capacity of resource 1=35 shirts / hour

Time taken per shirt at resource 1=60 / 35=1.7143 minutes

Capacity of resource 2=24 shirts / hour

Time taken per shirt at resource 2=60 / 24=2.5 minutes

Therefore,

Total labor content = Time taken per shirt at resource 1+ Time taken per shirt at resource 2=1.7143+2.5=4.2143 minutes per shirt

Disclaimer

Shirts are made in a process with two resources. There is one worker in eachresource. The first resource has a capacity of 35 shirts per hour. The capacity of thesecond resource is 24 shirts per hour. Demand for this process is 20 shirts per hour. What is the total labor content in a shirt? Provide your answer in minutes per shirt.

Learn more about labor content here

https://brainly.com/question/28059667

#SPJ1