A statement of a schedule of requirements for individual end items is called? group of answer choices a production plan a material requirements plan a master production schedule a capacity plan

Respuesta :

A statement of a schedule of requirements for individual end items is called a master production schedule.

What is the master production schedule?

A master production schedule is a strategy for how specific commodities, such as production, staffing, inventory, etc., will be created during each time period. Typically, it has to do with production, where the plan specifies when and how much of each product will be needed.

The goods a company will create when they will be produced, and in what quantities are specified in a master production schedule (MPS). An MPS connects production capacity and demand in the market. The goal of the master production schedule is to develop a practical strategy that reduces overstock and increases on-time delivery.

Therefore, the correct answer is option A) a master production schedule.

The complete question is:

A statement of a schedule of requirements for individual end items is called:

A) a master production schedule

B) a material requirements plan

C) production plan

D) a capacity plan

E) none of the abos

To learn more about master production schedule refer to:

https://brainly.com/question/25284650

#SPJ4