Respuesta :
Resource allocation for activities is done iteratively using the resource-limited scheduling option (c), where the least amount of activities receives the most resources.
Why is resource limited scheduling used?
Resource-limited scheduling seeks to ensure that the project can be finished as quickly as possible utilising the available resources. Although it also limits flexibility and raises the criticality of each event in the project, project managers that employ this method find that it produces a more realistic timetable.
Resource-constrained scheduling, also known as limited resource scheduling, doesn't sound like anything you want to be dealing with in your company. Your ears perk up as soon as terms like "restricted" or "constrained" are said. Despite the negative connotations of these terms, "restricted resource scheduling" is a good thing.
What is the importance of Limited Resource Scheduling?
Planning and scheduling are more crucial than ever due to restricted resources. It is obvious that having a finite amount of resources has a significant impact on the project's timeline and the precise schedule you must adhere to in order to stay on track. Any company may experience difficulties when working on a project with few resources. Therefore, it's critical to comprehend how you use resource-constrained scheduling to prevent significant delays and disruptions.
The final conclusion is that if you use limited resource scheduling and planning, you can meet a deadline. Yes, your situation will be much more complicated. Finding the best project route will be challenging, and event criticality will rise. Less flexibility in how you work will result, but if you achieve your goals, it will all be worthwhile. Project delays can result in financial loss, dissatisfied clients, and other problems. You may prevent these issues and find out how to optimise your project timeline by using restricted resource scheduling.
To know more about Resource limited scheduling visit:
https://brainly.com/question/15112022
#SPJ4